L Tower Construction Schedule April 16 – 21

This is the current construction schedule for 8 The Esplanade – L Tower for April 16 – 21, 2012

Posted April 13, 2012

Note: The L Tower is scheduled to reach 36 floors this week.

Monday, April 16

  • Rebar delivery starting at 7:00 am.
  • Hoist extension commences at 8:00 am.
  • Rebar delivery starting at 12:30 pm.

Tuesday, April 17

  • A 190M slab concrete pour, level 36, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

Wednesday, April 18

  • A 99M (part 1) wall and column concrete pour, levels 36 – 37 starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, April 19

  • A 108M (part 2) wall and column concrete pour, levels 36 – 37, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Friday, April 20

  • Rebar delivery starting at 7:00 am.
  • Rebar delivery starting at 12:30 pm.

Saturday, April 21

  • The L Tower’s further crane mast extension will commence at 9:00 am.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 14 – 21 summary highlights: L Tower & Backstage Construction Summary Highlights April 14-21

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: