Backstage Construction Schedule – April 16 – 20
April 13, 2012 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for April 16 – 20, 2012
Posted April 13, 2012
Monday, April 16
- Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
- There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
- There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
- Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.
Tuesday, April 17
- Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
- There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
- Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.
Wednesday, April 18
- Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
- There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
- Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.
Thursday, April 19
- Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
- There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
- Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.
Friday, April 20
- Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
- There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
- Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.
* * *
NOTES:
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Click on the link for a printable PDF of the L Tower and Backstage April 14 – 21 summary highlights: L Tower & Backstage Construction Summary Highlights April 14-21