Backstage Construction Schedule – April 16 – 20

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 16 – 20, 2012

Posted April 13, 2012

Monday, April 16

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

Tuesday, April 17

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

Wednesday, April 18

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

Thursday, April 19

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

Friday, April 20

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 14 – 21 summary highlights: L Tower & Backstage Construction Summary Highlights April 14-21

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: