Backstage Construction Schedule – April 9 – 13

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 9 – 13, 2012

Updated April 10, 2012

NOTE: Subcontractor, Deep Foundation will be delivering a large drill rig to the site at 1 The Esplanade in order to complete the piles and caisson work this week. The delivery date is not confirmed at the time of posting. Please check back for updated information.

Monday, April 9

  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

Tuesday, April 10

  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

Wednesday, April 11

  • Subcontractor, Deep Foundation, will be delivering a drill rig to the site at 1 The Esplanade after 9 am, under police escort.
    • There will be short-term disruptions to vehicular and pedestrian traffic. The construction management team apologizes for any short-term inconvenience this may cause.
  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

Thursday, April 12

  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

Friday,  April 13

  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 9 – 13 summary update: 1+8 The Esplanade – Construction Notice-April-9-13

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: