L Tower Construction Schedule April 30 – May 4

This is the current construction schedule for 8 The Esplanade – L Tower – for April 30 – May 4, 2012

Posted April 27, 2012

Note: The L Tower is scheduled to reach 39 floors this week.

Monday, April 30

  • Rebar delivery starting at 10:00 am.
  • A 190M slab concrete pour, level 38, starting 10:00 am,, which is not expected to extend beyond 7:00 pm.

Tuesday, May 1

  • A 99M (part 1) wall and column concrete pour, levels 38 – 39 starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, May 2

  • Rebar delivery starting at 12:30 pm.
  • A 108M (part 2) wall and column concrete pour, levels 38 – 39, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, May 3

  • Rebar delivery starting at 7:00 am.
  • Rebar delivery starting at 12:30 pm.

Friday, May 4

  • Rebar delivery starting at 10:00 am.
  • A 190M slab concrete pour, level 39, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 30 – May 4 summary highlights: L Tower & Backstage Construction April 30-May 4

Backstage Construction Schedule – April 30 – May 4

This is the current construction schedule for 1 The Esplanade – L Tower parking and
Backstage condominium for April 30 – May 4, 2012

Posted April 27/12

Monday, April 30

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Tuesday, May 1

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Wednesday, May 2

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Thursday, May 3

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Friday, May 4

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 30 – May 4 summary highlights: L Tower & Backstage Construction April 30-May 4

L Tower Construction Schedule April 23 – 27

This is the current construction schedule for 8 The Esplanade – L Tower for April 23 – 27, 2012

Posted April 20, 2012

Note: The L Tower is scheduled to reach 38 floors this week.

Monday, April 23

  • Window delivery starting at 7:00 am.
  • Rebar delivery starting at 10:00 am.
  • A 190M slab concrete pour, level 37, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

Tuesday, April 24

  • Window delivery starting at 7:00 am.
  • A 99M (part 1) wall and column concrete pour, levels 37 – 38 starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, April 25

  • Rebar delivery starting at 12:30 pm. 
  • A 108M (part 2) wall and column concrete pour, levels 36 – 37, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, April 26

  • Rebar delivery starting at 7:00 am.
  • Rebar delivery starting at 12:30 pm.

Friday, April 27

  • Rebar delivery starting at 7:00 am.
  • A 190M slab concrete pour, level 38, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Thursday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 23 – 27 summary highlights:  L Tower & Backstage Construction April 23-27

Backstage Construction Schedule – April 23 – 27

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 23 – 27, 2012

Posted April 20, 2012

Monday, April 23

  • Subcontractor, Deep Foundation, will be removing the tie drill in the morning.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Tuesday, April 24

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Wednesday, April 25

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Thursday, April 26

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Friday, April 27

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

* * *

NOTES:

Deep Foundation will complete the pile and caisson drilling this week. The drill rig will be removed from the site once drilling is completed. Please check back for an update on the time and date of the drill rig removal. 

A Paid Duty Police Officer is on-site daily Monday to Thursday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 23 – 27 summary highlights: L Tower & Backstage Construction April 23-27

L Tower & Flatiron

image

Saturday, April 14 – L Tower Crane Mast Extension

This a construction update for 8 The Esplanade – L Tower for April 14, 2012

Posted April 13, 2012

Saturday, April 14

  • The extension of the L Tower’s crane mast will commence at 9:00 am.

Click on the link for a printable PDF of the L Tower and Backstage April 14 – 21 summary highlights: L Tower & Backstage Construction Summary Highlights April 14-21

L Tower Construction Schedule April 16 – 21

This is the current construction schedule for 8 The Esplanade – L Tower for April 16 – 21, 2012

Posted April 13, 2012

Note: The L Tower is scheduled to reach 36 floors this week.

Monday, April 16

  • Rebar delivery starting at 7:00 am.
  • Hoist extension commences at 8:00 am.
  • Rebar delivery starting at 12:30 pm.

Tuesday, April 17

  • A 190M slab concrete pour, level 36, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

Wednesday, April 18

  • A 99M (part 1) wall and column concrete pour, levels 36 – 37 starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, April 19

  • A 108M (part 2) wall and column concrete pour, levels 36 – 37, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Friday, April 20

  • Rebar delivery starting at 7:00 am.
  • Rebar delivery starting at 12:30 pm.

Saturday, April 21

  • The L Tower’s further crane mast extension will commence at 9:00 am.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 14 – 21 summary highlights: L Tower & Backstage Construction Summary Highlights April 14-21

Backstage Construction Schedule – April 16 – 20

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 16 – 20, 2012

Posted April 13, 2012

Monday, April 16

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

Tuesday, April 17

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

Wednesday, April 18

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

Thursday, April 19

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

Friday, April 20

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 14 – 21 summary highlights: L Tower & Backstage Construction Summary Highlights April 14-21

Photo of the Day: Yonge Street Set For Change | Urban Toronto

A view of the L Tower looking north up Yonge Street from our friends at Urban Toronto: Photo of the Day: Yonge Street Set For Change | Urban Toronto.

L Tower photos from Cityzen’s http://blog.mycondomylife.com/

L Tower construction photos and comments from
Cityzen’s http://blog.mycondomylife.com/

“Daniel Libeskind’s building is elevating, accelerating and propelling forward steadily.
At L Tower, we’re pouring level 35 this week. Our crew is on a four-day cycle,
so a floor is being carried out every four days. Of course, it helps that the weather has been pleasant.”

“L Tower’s low-rise elevator door frames will be completed this week and will virtually wrap up by the end of next week. The cabs are currently being set up on the mid-rise elevators, and we’re putting finishing touches to them this week. Sooner than later, the high-rise elevator construction work will start soon.”