L Tower Construction Schedule April 2 – 6

This is the current construction schedule for 8 The Esplanade – L Tower for April 2 – 6, 2012

Posted March 30, 2012

Note: The L Tower is scheduled to reach 34 floors this week.

Monday, April 2

  • A 108M (part 2) wall and column concrete pour, levels 33 – 34, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.
  • Rebar delivery starting at 12:30 pm

Tuesday, April 3

  • Rebar delivery starting at 12:30 pm

Wednesday, April 4

  • Rebar delivery starting at 7:00 am.
  • A 190M slab concrete pour, level 34, starting 10:00 am, which is not expected to extend beyond 7:00 pm.
  • Rebar delivery starting at 12:30 pm.

Thursday, April 5

  • Heat Pump (for individual condo suites) delivery starting at 7:30 am.
  • A 99M (part 1) wall and column concrete pour, levels 34 – 35, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Good Friday – Holiday – April 6

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Thursday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 2 – 6 summary update: L Tower & Backstage Construction April 2 – 6

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

<span>%d</span> bloggers like this: