Backstage Construction Schedule – April 2 – 6
March 30, 2012 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for April 2 – 6, 2012
Posted March 30, 2012
Monday, April 2
- Sub-contractor, Deep Foundation, will be floating in the tie back machine in the morning.
- NOTE: This will unfortunately cause short-term delays for vehicular and pedestrian traffic.
Tuesday, April 3
- Sub-contractor, Deep Foundation, will be installing tie backs.
Wednesday, April 4
- Sub-contractor, Deep Foundation, will be installing tie backs.
- Sub-contractor, GFL Excavating, will be removing material from the site: 4 trucks doing 5 loads each.
Thursday, April 5
- Sub-contractor, Deep Foundation, will be installing tie backs.
- Sub-contractor, GFL Excavating, will be removing material from the site: 4 trucks doing 5 loads each.
Good Friday – Holiday – April 6
* * *
NOTES:
A Paid Duty Police Officer is on-site daily Monday to Thursday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Click on the link for a printable PDF of the L Tower and Backstage April 2 – 6 summary update: L Tower & Backstage Construction April 2 – 6