L Tower Construction Schedule March 26 – 31

This is the current construction schedule for 8 The Esplanade – L Tower for March 26 – 31, 2012

Posted March 23, 2012

Monday, March 26

  • Window Delivery starting at 7:00 am; 3 containers.
  • A 99M (part 1) wall and column concrete pour, levels 32 – 33, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Tuesday, March 27

  • Steel Delivery starting at 12:30 pm.
  • A 108M (part 2) wall and column concrete pour, levels 32 – 33, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, March 28

  • Steel delivery at 7:00 am.
  • Steel delivery at 12:30 pm.

Thursday, March 29

  • Steel delivery at 10:00 am.
  • A 190M slab concrete pour, level 33, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

Friday, March 30

  • A 99M wall and column concrete pour, levels 33 – 34, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Saturday, March 31

  • Miscellaneous clean up activities on site from 9:00 am to Noon.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage March 26 – 31 summary update: L Tower & Backstage Construction March 26-31

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: