Backstage Construction Schedule – March 26 – 30
March 24, 2012 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for March 26 – 30, 2012
Posted March 23, 2012
NOTE: The job site at 1 The Esplanade is in transition from GFL Excavating to Deep Foundation for the completion of pile and caisson work and starting at the second row tie back. There will be a drill rig and tie back drill delivered to the site but the delivery date are not confirmed at this time. Please check back for updates.
Monday, March 26
- Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.
Tuesday, March 20
- Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.
Wednesday, March 21
- Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.
Thursday, March 22
- Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.
Friday, March 23
- Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.
* * *
NOTES:
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Click on the link for a printable PDF of the L Tower and Backstage March 26 – 31 summary update: L Tower & Backstage Construction March 26-31