Backstage Construction Schedule – March 26 – 30

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for March 26 – 30, 2012

Posted March 23, 2012

NOTE: The job site at 1 The Esplanade is in transition from GFL Excavating to Deep Foundation for the completion of pile and caisson work and starting at the second row tie back. There will be a drill rig and tie back drill delivered to the site but the delivery date are not confirmed at this time. Please check back for updates.

Monday, March 26

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

Tuesday, March 20

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

Wednesday, March 21

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

Thursday, March 22

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

Friday, March 23

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage March 26 – 31 summary update: L Tower & Backstage Construction March 26-31

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: