Backstage Construction Schedule – March 19 – 23

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for March 19 – 23, 2012

Posted March 17, 2012

Monday, March 19

  • Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each–50 loads.

Tuesday, March 20

  • Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each–50 loads.

Wednesday, March 21

  • Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each–50 loads.

Thursday, March 22

  • Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each–50 loads.

Friday, March 23

  • Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each–50 loads.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on this link for a printable PDF of the L Tower and Backstage March 17 summary update: 1+8 The Esplanade Construction UPDATE March-17

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: