L Tower Construction Schedule March 12 – 17
March 9, 2012 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – for March 12 – 17, 2012
Posted March 9, 2012
Monday, March 12
- Steel delivery at 7:00 am.
- Steel delivery at Noon.
Tuesday, March 13
- Steel delivery at 10:00 am.
- A 200M concrete pour scheduled to start at 10:00 am, which is not expected to extend beyond 7:00 pm.
Wednesday, March 14
- A 90M concrete pour scheduled to start at 2:00 pm, which may extend beyond 7:00 pm.
Thursday, March 15
- Steel delivery at Noon
- A 100M concrete pour scheduled to start at 1:00 pm, which may extend beyond 7:00 pm.
Friday, March 16
- Steel delivery at 7:00 am.
- Steel delivery at Noon.
Saturday, March 17
- No major site work is scheduled at this time.
* * *
NOTES:
Construction schedules are dependent on weather conditions.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Click on this link for a printable PDF summary schedule of the L Tower and Backstage for March 12 – 17 inclusive: 1+8 The Esplanade – Construction Notice-March-12-17