L Tower Construction Schedule March 12 – 17

This is the current construction schedule for 8 The Esplanade – L Tower for March 12 – 17, 2012

Posted March 9, 2012

Monday, March 12

  • Steel delivery at 7:00 am.
  • Steel delivery at Noon.

Tuesday, March 13

  • Steel delivery at 10:00 am.
  • A 200M concrete pour scheduled to start at 10:00 am, which is not expected to extend beyond 7:00 pm.

Wednesday, March 14

  • A 90M concrete pour scheduled to start at 2:00 pm, which may extend beyond 7:00 pm.

Thursday, March 15

  • Steel delivery at Noon
  • A 100M concrete pour scheduled to start at 1:00 pm, which may extend beyond 7:00 pm.

Friday, March 16

  • Steel delivery at 7:00 am.
  • Steel delivery at Noon.

Saturday, March 17

  • No major site work is scheduled at this time.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on this link for a printable PDF summary schedule of the L Tower and Backstage for March 12 – 17 inclusive: 1+8 The Esplanade – Construction Notice-March-12-17

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: