This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for March 12 – 16, 2012
Posted March 9, 2012
Monday, March 12
- Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each.
Tuesday, March 13
- Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each.
Wednesday, March 14
- Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each.
Thursday, March 15
- Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each.
Friday, March 16
- Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each.
* * *
NOTES:
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Click on this link for a printable PDF summary schedule of the L Tower and Backstage for March 12 – 17 inclusive: 1+8 The Esplanade – Construction Notice-March-12-17