Backstage – Construction Schedule – Mach 12 – 16

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for March 12 – 16, 2012

Posted March 9, 2012

Monday, March 12

  • Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each.

Tuesday, March 13

  • Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each.

Wednesday, March 14

  • Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each.

Thursday, March 15

  • Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each.

Friday, March 16

  • Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on this link for a printable PDF summary schedule of the L Tower and Backstage for March 12 – 17 inclusive: 1+8 The Esplanade – Construction Notice-March-12-17

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: