Construction Schedule – L Tower – March 5 – 10

This is the current construction schedule for 8 The Esplanade – L Tower for March 5 – 10, 2012

UPDATED March 3, 2012

Monday, March 5

  • A 220M concrete pour for the slab at Level 29 beginning at 9:00 am, which is not expected to extend beyond 7:00 pm.

Tuesday, March 6

  • Steel delivery at 7:00 am.
  • Steel delivery at Noon.
  • A 100M concrete pour scheduled to start at 1:00 pm, which may extend beyond 7:00 pm.

Wednesday, March 7

  • Steel delivery at 7:00 am.
  • Steel delivery at Noon
  • A 100M concrete pour scheduled to start at 1:00 pm, which may extend beyond 7:00 pm.

Thursday, March 8

  • A 100M concrete pour scheduled to start at 10:00 am, which is not expected to extend beyond 7:00 pm.

Friday, March 9

  • A 100M concrete pour scheduled to start at 1:00 pm, which may extend beyond 7:00 pm.

Saturday, March 10

  • No major site work is scheduled at this time.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on this link for a printable PDF summary schedule of the L Tower and Backstage for March 3 – 10 inclusive: 1+8 The Esplanade – Construction Notice-March-3-10

One Response to Construction Schedule – L Tower – March 5 – 10

  1. Pingback: Revised L Tower Concrete Pour Schedule March 5 – 9 « L Tower & Backstage Construction Information

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: