Backstage – Construction Schedule – March 5 – 9
March 3, 2012 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for March 5 – 9, 2012
Posted March 2, 2012
Monday, March 5
- Sub-contractor, GFL Excavating, doing bulk excavating, with five (5) dump trucks removing material from the site, doing five (5) rounds each.
Tuesday, March 6
- Sub-contractor, GFL Excavating, doing bulk excavating, with five (5) dump trucks removing material from the site, doing five (5) rounds each.
Wednesday, March 7
- Sub-contractor, GFL Excavating, doing bulk excavating, with five (5) dump trucks removing material from the site, doing five (5) rounds each.
Thursday, March 8
- Sub-contractor, GFL Excavating, doing bulk excavating, with five (5) dump trucks removing material from the site, doing five (5) rounds each.
Friday, March 9
- Sub-contractor, GFL Excavating, doing bulk excavating, with five (5) dump trucks removing material from the site, doing five (5) rounds each.
* * *
NOTES:
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Click on this link for a printable PDF summary schedule of the L Tower and Backstage for March 3 – 10 inclusive: 1+8 The Esplanade – Construction Notice-March-3-10