UPDATE for Saturday, March 3,  8 The Esplanade – L Tower for February 27 – March 3, 2012

Updated March 3, 2012

NOTE: Bad weather this past week delayed the pouring of the concrete slab at Level 29, so significant Saturday work is required; as is permitted by the City of Toronto by-law.

Saturday, March 3

  • The crane will be raised beginning at 9:00 am but is dependent on weather. For example, if there is significant wind the crane raising may be delayed or re-scheduled.
  • Concrete pour CANCELLED due to high winds.

  • A 220M concrete pour for the slab at Level 29 beginning at 9:00 am, which is not expected to extend beyond 7:00 pm.
  • A Paid Duty Officer will be in attendance.

One Response to L Tower – 8 The Esplanade – Saturday March 3 – Crane Raising and Concrete Pour

  1. Pingback: Construction Schedule – L Tower – Feb 27 – Mar 3 « L Tower & Backstage Construction Information

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: