L Tower Construction Schedule April 2 – 6

This is the current construction schedule for 8 The Esplanade – L Tower for April 2 – 6, 2012

Posted March 30, 2012

Note: The L Tower is scheduled to reach 34 floors this week.

Monday, April 2

  • A 108M (part 2) wall and column concrete pour, levels 33 – 34, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.
  • Rebar delivery starting at 12:30 pm

Tuesday, April 3

  • Rebar delivery starting at 12:30 pm

Wednesday, April 4

  • Rebar delivery starting at 7:00 am.
  • A 190M slab concrete pour, level 34, starting 10:00 am, which is not expected to extend beyond 7:00 pm.
  • Rebar delivery starting at 12:30 pm.

Thursday, April 5

  • Heat Pump (for individual condo suites) delivery starting at 7:30 am.
  • A 99M (part 1) wall and column concrete pour, levels 34 – 35, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Good Friday – Holiday – April 6

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Thursday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 2 – 6 summary update: L Tower & Backstage Construction April 2 – 6

Backstage Construction Schedule – April 2 – 6

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 2 – 6, 2012

Posted March 30, 2012

Monday, April 2

  • Sub-contractor, Deep Foundation, will be floating in the tie back machine in the morning.
  • NOTE: This will unfortunately cause short-term delays for vehicular and pedestrian traffic.

Tuesday, April 3

  • Sub-contractor, Deep Foundation, will be installing tie backs.

Wednesday, April 4

  • Sub-contractor, Deep Foundation, will be installing tie backs.
  • Sub-contractor, GFL Excavating, will be removing material from the site: 4 trucks doing 5 loads each.

Thursday, April 5

  • Sub-contractor, Deep Foundation, will be installing tie backs.
  • Sub-contractor, GFL Excavating, will be removing material from the site: 4 trucks doing 5 loads each.

Good Friday – Holiday – April 6

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Thursday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 2 – 6 summary update: L Tower & Backstage Construction April 2 – 6

Backstage Construction Schedule – March 26 – 30

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for March 26 – 30, 2012

Posted March 23, 2012

NOTE: The job site at 1 The Esplanade is in transition from GFL Excavating to Deep Foundation for the completion of pile and caisson work and starting at the second row tie back. There will be a drill rig and tie back drill delivered to the site but the delivery date are not confirmed at this time. Please check back for updates.

Monday, March 26

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

Tuesday, March 20

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

Wednesday, March 21

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

Thursday, March 22

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

Friday, March 23

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage March 26 – 31 summary update: L Tower & Backstage Construction March 26-31

L Tower Construction Schedule March 26 – 31

This is the current construction schedule for 8 The Esplanade – L Tower for March 26 – 31, 2012

Posted March 23, 2012

Monday, March 26

  • Window Delivery starting at 7:00 am; 3 containers.
  • A 99M (part 1) wall and column concrete pour, levels 32 – 33, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Tuesday, March 27

  • Steel Delivery starting at 12:30 pm.
  • A 108M (part 2) wall and column concrete pour, levels 32 – 33, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, March 28

  • Steel delivery at 7:00 am.
  • Steel delivery at 12:30 pm.

Thursday, March 29

  • Steel delivery at 10:00 am.
  • A 190M slab concrete pour, level 33, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

Friday, March 30

  • A 99M wall and column concrete pour, levels 33 – 34, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Saturday, March 31

  • Miscellaneous clean up activities on site from 9:00 am to Noon.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage March 26 – 31 summary update: L Tower & Backstage Construction March 26-31

Excavating at 1 The Esplanade, site of the Backstage Condo

Bulk excavation continues on a daily basis at 1 The Esplanade. The site will be the location of the underground parking for the L Tower and the foundation for the Backstage Condominium.

Excavating at 1 The Esplanade 3/22/12

Excavating at 1 The Esplanade - looking west southwest to the Yonge Street Railway Bridge

Urban Toronto captures Crane Raising at L Tower

Thanks to our friends at Urban Toronto for these pictures of the L Tower Crane Raising on Saturday, March 17, 2012.

Please click on this link to see the pictures.

L Tower Construction Schedule March 19 – 24

This is the current construction schedule for 8 The Esplanade – L Tower for March 19 – 24, 2012

Posted March 17, 2012

Monday, March 19

  • Steel delivery at 10:00 am.
  • A 190M  concrete slab pour starting 10:00 am, which is not expected to extend beyond 7:00 pm.

Tuesday, March 20

  • A 99M concrete wall and column pour scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, March 21

  • Steel delivery at 12:30 pm.
  • A 108M concrete wall and column pour scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, March 22

  • Steel delivery at 7:00 am.
  • Steel delivery at 12:30 pm.

Friday, March 23

  • Steel delivery at 10:00 am.
  • A 190M  concrete slab pour starting 10:00 am, which is not expected to extend beyond 7:00 pm.

Saturday, March 24

  • No major site work is scheduled at this time.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on this link for a printable PDF of the L Tower and Backstage March 17 summary update: 1+8 The Esplanade Construction UPDATE March-17

Backstage Construction Schedule – March 19 – 23

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for March 19 – 23, 2012

Posted March 17, 2012

Monday, March 19

  • Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each–50 loads.

Tuesday, March 20

  • Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each–50 loads.

Wednesday, March 21

  • Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each–50 loads.

Thursday, March 22

  • Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each–50 loads.

Friday, March 23

  • Sub-contractor, GFL Excavating, doing bulk excavating, with ten (10) dump trucks removing material from the site, doing five (5) rounds each–50 loads.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on this link for a printable PDF of the L Tower and Backstage March 17 summary update: 1+8 The Esplanade Construction UPDATE March-17

L Tower Construction Photos, March 16, 2012

L Tower at 30 floors and counting - as seen from the Backstage construction site - March 16, 2012

Site of the future public plaza at the Sony Centre, L Tower in the background, March 16, 2012

L Tower rising above the future public plaza beside the Sony Centre, March 16, 2012

Looking up at the L Tower from Yonge Street, March 16, 2012

L Tower as seen from Union Station - Front Street West, March 16, 2012

Backstage Construction Site Photos March 16/12

Backstage Construction site March 16, 2012 looking west to Yonge Street Railway Bridge

Excavating bulk - 1 The Esplanade - March 16, 2012

Excavating 1 The Esplanade - March 16, 2012

Loading the dirt into the dump truck - 1 load of 50 per day - 1 The Esplanade March 16, 2012