Construction Schedule – L Tower – Feb 27 – Mar 3

This is the current construction schedule for 8 The Esplanade – L Tower for February 27 – March 3, 2012

Updated March 2, 2012

Monday, February 27

  • A concrete pour for walls and columns on Levels 28 and 29, part 1, scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Tuesday, February 28

  • A concrete pour for walls and columns on Levels 28 and 29, part 2, scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, February 29

  • Steel delivery at 7:00 am.
  • Window Delivery starting at 7:30 am.
  • Steel delivery at 10:00 am

Thursday, March 1

  • Window Delivery starting at 7:30 am.
  • Steel delivery at 10:00 am.
  • Weather postponed the scheduled concrete pour. 

Friday, March 2

  • Weather postponed this scheduled concrete pour: A concrete pour for walls and columns on Levels 29 and 30, part 1, scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Saturday, March 3

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: