Construction Schedule – L Tower – Feb 27 – Mar 3
February 27, 2012 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – for February 27 – March 3, 2012
Updated March 2, 2012
Monday, February 27
- A concrete pour for walls and columns on Levels 28 and 29, part 1, scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.
Tuesday, February 28
- A concrete pour for walls and columns on Levels 28 and 29, part 2, scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.
Wednesday, February 29
- Steel delivery at 7:00 am.
- Window Delivery starting at 7:30 am.
- Steel delivery at 10:00 am
Thursday, March 1
- Window Delivery starting at 7:30 am.
- Steel delivery at 10:00 am.
- Weather postponed the scheduled concrete pour.
Friday, March 2
- Weather postponed this scheduled concrete pour: A concrete pour for walls and columns on Levels 29 and 30, part 1, scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.
Saturday, March 3
* * *
NOTES:
Construction schedules are dependent on weather conditions.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.