Backstage – Construction Schedule Feb 27 – Mar 2

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for February 27 – March 2, 2012

Posted February 24, 2012

Monday, February 27

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

Tuesday, February 28

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

Wednesday, February 29

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

Thursday, March 1

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

Friday, March 2

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: