L Tower – 8 The Esplanade – Construction Schedule Feb 21 – 25
February 17, 2012 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – for February 21 – 25, 2012
Posted February 17, 2012
Monday, February 20 – Family Day Holiday
Tuesday, February 21
- A 90m concrete pour scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.
Wednesday, February 22
- Steel delivery at 7:00 am.
- Steel delivery at 10:00 am
Thursday, February 23
- Steel delivery at 7:00 am.
- Steel delivery at 10:00 am.
- An 190m concrete pour scheduled to start at 10:00 am, which is not expected to extend beyond 7:00 pm.
Friday, February 24
- An 100m concrete pour scheduled to start at 2:00 pm, which might extend beyond 7:00 pm.
Saturday, February 25
- No major site work is scheduled at this time.
* * *
NOTES:
Construction schedules are dependent on weather conditions.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.