L Tower – 8 The Esplanade – Construction Schedule Feb 13 – 17
February 10, 2012 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – for February 13 – 17, 2012
Posted February 10, 2012
Monday, February 13
- A steel delivery at 10:00 am.
- An 100m concrete pour scheduled to start at 2:00 pm, which is not expected to extend beyond 7:00 pm.
Tuesday, February 14
- A 90m concrete pour scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.
Wednesday, February 15
- A steel delivery at 7:00 am.
- A second steel delivery at 10:00 am.
Thursday, February 16
- A steel delivery at 7:00 am.
- A second steel delivery at 10:00 am.
- An 180m concrete pour scheduled to start at 10:00 am, which is not expected to extend beyond 7:00 pm.
Friday, February 17
- An 180m concrete pour scheduled to start at 2:00 pm, which may extend beyond 7:00 pm.
* * *
NOTES:
Construction schedules are dependent on weather conditions.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.