Backstage – 1 The Esplanade – Construction Schedule Feb 13 – 17

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for February 13 – 17, 2012

Posted February 10, 2012

Monday, February 13

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.
  • Sub-contractor, GFL and will have four (4) dump trucks removing material from the site, doing five (5) rounds each.

Tuesday, February 14

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.

Wednesday, February 15

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.

Thursday, February 16

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.

Friday, February 17

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: