Update: Backstage – 1 The Esplanade – Construction Schedule Feb 9 – 10
February 9, 2012 Leave a comment
Construction Update for 1 The Esplanade – L Tower parking and Backstage condominium – for February 9 & 10, 2012
Posted February 8, 2012
Thursday, February 9
- Sub-contractor, Deep Foundation drilling caissons and piles.
- Seven (7) loads of concrete.
- UPDATED: Sub-contractor, GFL is scheduled to have 4 dump trucks doing 5 rounds each, removing material from the site.
Friday, February 10
- Sub-contractor, Deep Foundation drilling caissons and piles.
- Seven (7) loads of concrete.
- UPDATED: Sub-contractor, GFL is scheduled to have 4 dump trucks doing 5 rounds each, removing material from the site.
* * *
NOTES:
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.