L Tower – 8 The Esplanade – Construction Schedule Feb 4 – 10

This is the current construction schedule for 8 The Esplanade – L Tower for February 4 – 10, 2012

Posted February 3, 2012

UPDATE: Saturday, February 4

  • On-going infrastructure installation for Bell (telephone), trenching through site.

Monday, February 6

  • On-going infrastructure installation for Bell (telephone), trenching through site, and north on Yonge Street.
  • Concrete pour scheduled to start at 11:00 am, which is not expected to extend beyond 7:00 pm.

Tuesday, February 7

  • Window delivery at 7:30 am.
  • Concrete pour scheduled to start at 2:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, February 8

  • Window delivery at 7:30 am.
  • Concrete pour scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, February 9

  • Rebar delivery.

Friday, February 10

  • Rebar delivery.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: