Backstage – 1 The Esplanade – Construction Schedule Feb 6 – 10
February 3, 2012 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for February 6 – 10, 2012
Updated February 8, 2012
Monday, February 6
- Sub-contractor, Deep Foundation drilling caissons and piles.
- Seven (7) loads of concrete.
- Sub-contractor, GFL will be delivering a backhoe.
- Sub-contractor, GFL and will have six (6) dump trucks removing material from the site, doing five (5) rounds each.
Tuesday, February 7
- Sub-contractor, Deep Foundation drilling caissons and piles.
- Seven (7) loads of concrete.
- Sub-contractor, GFL and will have six (6) dump trucks removing material from the site, doing five (5) rounds each.
Wednesday, February 8
- Sub-contractor, Deep Foundation drilling caissons and piles.
- Seven (7) loads of concrete.
Thursday, February 9
- Sub-contractor, Deep Foundation drilling caissons and piles.
- Seven (7) loads of concrete.
- UPDATED: Sub-contractor, GFL is scheduled to have 4 dump trucks doing 5 rounds each, removing material from the site.
Friday, February 10
- Sub-contractor, Deep Foundation drilling caissons and piles.
- Seven (7) loads of concrete.
- UPDATED: Sub-contractor, GFL is scheduled to have 4 dump trucks doing 5 rounds each, removing material from the site.
* * *
NOTES:
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.