Backstage – 1 The Esplanade – Construction Schedule Feb 6 – 10

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for February 6 – 10, 2012

Updated February 8, 2012

Monday, February 6

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.
  • Sub-contractor, GFL will be delivering a backhoe.
  • Sub-contractor, GFL and will have six (6) dump trucks removing material from the site, doing five (5) rounds each.

Tuesday, February 7

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.
  • Sub-contractor, GFL and will have six (6) dump trucks removing material from the site, doing five (5) rounds each.

Wednesday, February 8

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.

Thursday, February 9

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.
  • UPDATED: Sub-contractor, GFL is scheduled to have 4 dump trucks doing 5 rounds each, removing material from the site. 

Friday, February 10

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.
  • UPDATED: Sub-contractor, GFL is scheduled to have 4 dump trucks doing 5 rounds each, removing material from the site. 

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: