Backstage – 1 The Espalande – Thursday March 1, Crane Removal

This is an update for Thursday, March 1 2012 for construction activity at the Backstage condominium at 1 The Esplanade.

Thursday, March 1

  • Sub-contractor, Deep Foundation will have a float arriving at 8:00 am to remove the crawler crane from the construction site. The float will be leaving the site at 9:00 am under police escort. There will be unavoidable short-term disruptions to vehicular and pedestrian traffic during this process, in order to ensure the safety of the construction crew, drivers, cyclists and pedestrians.

Construction Schedule – L Tower – Feb 27 – Mar 3

This is the current construction schedule for 8 The Esplanade – L Tower for February 27 – March 3, 2012

Updated March 2, 2012

Monday, February 27

  • A concrete pour for walls and columns on Levels 28 and 29, part 1, scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Tuesday, February 28

  • A concrete pour for walls and columns on Levels 28 and 29, part 2, scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, February 29

  • Steel delivery at 7:00 am.
  • Window Delivery starting at 7:30 am.
  • Steel delivery at 10:00 am

Thursday, March 1

  • Window Delivery starting at 7:30 am.
  • Steel delivery at 10:00 am.
  • Weather postponed the scheduled concrete pour. 

Friday, March 2

  • Weather postponed this scheduled concrete pour: A concrete pour for walls and columns on Levels 29 and 30, part 1, scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Saturday, March 3

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

L Tower quick facts

Some quick facts about the construction of the L Tower

    rr

  • The  L Tower reached 28 floors as of the week ending February 24th 2012.
    rr

  • Since construction began 16,230M of concrete have been poured to-date.
    rr

  • The L Tower’s glazing system is part curtain wall and part window wall system.
      rr

    • Windows are brought up into the building through the means of our material hoist.
    • These windows are then distributed on the appropriate floors and then installed from inside the building.

rr

Backstage – Construction Schedule Feb 27 – Mar 2

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for February 27 – March 2, 2012

Posted February 24, 2012

Monday, February 27

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

Tuesday, February 28

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

Wednesday, February 29

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

Thursday, March 1

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

Friday, March 2

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

L Tower – 8 The Esplanade – Construction Schedule Feb 21 – 25

This is the current construction schedule for 8 The Esplanade – L Tower for February 21 – 25, 2012

Posted February 17, 2012

Monday, February 20 – Family Day Holiday

Tuesday, February 21

  • A 90m concrete pour scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, February 22

  • Steel delivery at 7:00 am.
  • Steel delivery at 10:00 am

Thursday, February 23

  • Steel delivery at 7:00 am.
  • Steel delivery at 10:00 am.
  • An 190m concrete pour scheduled to start at 10:00 am, which is not expected to extend beyond 7:00 pm.

Friday, February 24

  • An 100m concrete pour scheduled to start at 2:00 pm, which might  extend beyond 7:00 pm.

Saturday, February 25

  • No major site work is scheduled at this time.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Backstage – 1 The Esplanade – Construction Schedule Feb 21 – 24

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for February 20 – 24, 2012

Posted February 17, 2012

Monday, February 20 – Family Day Holiday

Tuesday, February 21

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.

Wednesday, February 22

  • Sub-contractor, Deep Foundation disassembling drill.
  • Sub-contractor, GFL Excavating, and will have four (4) dump trucks removing material from the site, doing five (5) rounds each.

Thursday, February 23

  • Sub-contractor, Deep Foundation floating out the drill rig under police escort. Time to be posted.
  • Sub-contractor, GFL Excavating, and will have six (6) dump trucks removing material from the site, doing five (5) rounds each.

Friday, February 24

  • Sub-contractor, GFL Excavating, and will have six (6) dump trucks removing material from the site, doing five (5) rounds each.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

L Tower from Yonge and King

L Tower from Yonge & King, February 16, 2012

Update for Backstage 1 The Esplanade for Wednesday February 15

Construction Update for 1 The Esplanade – L Tower parking and Backstage condominium for Wednesday February 15, 2012

Posted February 15, 2012

Update:

  • Sub-contractor, GFL Excavating will have dump trucks removing material from the site: 4 dump trucks doing 5 rounds each..

Backstage – 1 The Esplanade – Construction Schedule Feb 13 – 17

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for February 13 – 17, 2012

Posted February 10, 2012

Monday, February 13

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.
  • Sub-contractor, GFL and will have four (4) dump trucks removing material from the site, doing five (5) rounds each.

Tuesday, February 14

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.

Wednesday, February 15

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.

Thursday, February 16

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.

Friday, February 17

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

L Tower – 8 The Esplanade – Construction Schedule Feb 13 – 17

This is the current construction schedule for 8 The Esplanade – L Tower for February 13 – 17, 2012

Posted February 10, 2012

Monday, February 13

  • A steel delivery at 10:00 am.
  • An 100m concrete pour scheduled to start at 2:00 pm, which is not expected to extend beyond 7:00 pm.

Tuesday, February 14

  • A 90m concrete pour scheduled to start at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, February 15

  • A steel delivery at 7:00 am.
  • A second steel delivery at 10:00 am.

Thursday, February 16

  • A steel delivery at 7:00 am.
  • A second steel delivery at 10:00 am.
  • An 180m concrete pour scheduled to start at 10:00 am, which is not expected to extend beyond 7:00 pm.

Friday, February 17

  • An 180m concrete pour scheduled to start at 2:00 pm, which may extend beyond 7:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.