Drilling and “breaking” for Backstage

These pictures show site work today–1/9/12–at 1 The Esplanade, preparing the way for the Backstage Condominium from Castlepoint, Cityzen and Fernbrook Homes. The site will also house the underground parking for the adjacent L Tower. The work this week is focused on drilling caissons and “breaking” parts of the railway bridge structure that will be replaced by the Backstage podium. During construction work there are also some temporary holds on eastbound traffic but with every effort made to minimize delays.

Between Backstage and L Tower, temporarily holding traffic on The Esplanade, 1/9/12

"Breaking" a section of railway bridge with a pneumatic hammer, 1 The Esplanade, 1/9/12

Drilling at the Backstage construction site, 1 The Esplanade, 1/9/12

Backstage construction site looking west, 1 The Esplanade, 1/9/12

A "found" metal "flower" at the Backstage construction site, 1 The Esplanade, 1/9/12

Backstage construction site, looking east, 1 The Esplanade, 1/9/12

8 The Esplanade Construction Schedule, Jan 9 – 14

This is the current construction schedule for 8 The Esplanade – L Tower for January 9 – 14, 2012

Updated January 8, 2012

Monday, January 9

  • There will be a Steel Delivery at 9:00 am.

Tuesday, January 10

  • There will be a Steel Delivery at 7:00 am.

Wednesday, January 11

  • There will be a Steel Delivery at 7:00 am.
  • There will be an 180M concrete pour beginning at 10:00 am with the chance of extending beyond 7:00 pm.

Thursday, January 12

  • There will be a Steel Delivery at 7:00 am.
  • There will be an 90M concrete pour beginning at 2:00 pm with the chance of extending beyond 7:00 pm.

Friday, January 13

  • There will be a Steel Delivery at 7:00 am.
  • There will be an 80M concrete pour beginning at 2:00 pm with the chance of extending beyond 7:00 pm.

Saturday, January 14

  • General work on site from 9:00 am to 4;00 pm, accompanied by 1 paid duty police officer.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade – Construction Schedule Jan 9 – 13, 2012

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 9 – 13, 2012

Posted January 6, 2012

Monday, January 9

  • Steel pile delivery at 7:00 am.
  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL delivering an excavator.

Tuesday, January 10

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

Wednesday, January 11

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

Thursday, January 12

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

Friday, January 13

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

January 5 L Tower concrete pour

Due to an unforeseen breakdown at Dominus’ concrete supplier’s mixing plant, Dominus was unable to keep yesterday’s — January 5 — L Tower concrete  pour within the previously assured 7:00pm time constraint.

The construction management team apologizes for any inconvenience this may have caused.

8 The Esplanade – Construction Schedule January 3 – 7, 2012

This is the current construction schedule for 8 The Esplanade – L Tower for January 3 – 6, 2012

Updated January 4, 2012

Tuesday, January 3

  • CANCELLED – There will be a steel Delivery at 7:00 am.
  • CANCELLED – There will be an 80M concrete pour beginning at 2:00pm with the chance of extending beyond 7:00 pm.

Wednesday, January 4

  • There will be a steel Delivery at 7:00 am.
  • CANCELLED – There will be an 80M concrete pour beginning at 2:00 pm with the chance of extending beyond 7:00 pm.

Thursday, January 5

  • There will be a steel Delivery at 7:00 am.
  • Rescheduled from Wednesday: There will be an 90M concrete pour beginning at 1:00 pm which is not expected to extend beyond 7:00 pm.

Friday, January 6

  • There will be a steel Delivery at 7:00 am.
  • Rescheduled from Thursday: There will be an 80M concrete pour beginning at 1:00 pm which is not expected to extend beyond 7:00 pm.

Saturday, January 7

  • General work on site from 9:00 am to 4;00 pm, accompanied by 1 paid duty police officer.

* * *

* * *

Best wishes for the New Year!

NOTES:

A Paid Duty Police Officer is on-site daily Tuesday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade – Construction Schedule Jan 3 – 6, 2012

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 3 – 6, 2012

Posted January 3, 2012

Tuesday, January 3

  • Sub-contractor, Deep Foundation drilling caissons: 5 loads of concrete.

Wednesday, January 4

  • Sub-contractor, Deep Foundation drilling caissons: 5 loads of concrete.

Thursday, January 5

  • Sub-contractor, Deep Foundation drilling caissons: 5 loads of concrete.

Friday, January 6

  • Sub-contractor, Deep Foundation drilling caissons: 5 loads of concrete..

* * *

Best wishes for the New Year!

NOTES:

A Paid Duty Police Officer is on-site daily Tuesday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.