L Tower – 8 The Esplanade – Construction Schedule Jan 28 – Feb 4
January 27, 2012 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – for January 30 – February 4, 2012
Posted January 27, 2012
UPDATE: Saturday, January 28
- 9M concrete pour beginning at 9:00 am.
Monday, January 30
- Rebar delivery at 7:00 am.
- Rebar delivery at 10:00 am.
Tuesday, January 31
- Rebar delivery at 10:00 am.
Wednesday, February 1
- There will be a 180M concrete pour beginning at 10:00 am, which is NOT expected to extend beyond 7:00 pm.
Thursday, February 2
- There will be a 90M concrete pour, which is NOT expected to extend beyond 7:00 pm.
Friday, February 3
- Steel delivery at 7:00 am.
- Steel delivery at 10:00 am.
- There will be a 100M concrete pour beginning at 1:00 pm, which may have a slight chance of extending beyond 7:00 pm.
Saturday, February 4
- At this time – January 27th – no work is scheduled.
* * *
NOTES:
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.