Backstage – 1 The Esplanade – Construction Schedule Jan 30 – Feb 3

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 30 – February 3, 2012

UPDATED January 31, 2012

Monday, January 30

  • Sub-contractor, Deep Foundation will be removing one of the drill rigs from the site, beginning at 7:00 am.
  • At approximately 10:00 am, a semi-trailer with the float for the drill rig will arrive to take it off-site. There will be short-term disruptions to pedestrian and vehicular traffic.
  • The remaining drill rig on site will continue drilling caissons and piles.
  • Five (5) loads of concrete.

Tuesday, January 31

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.

Wednesday, February 1

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.
  • UPDATE – Sub-contractor GFL Excavating will have three (3) dump trucks removing material from the site at 1 The Esplanade. There will be three (3) truck doing 5 rounds of removal each.

Thursday, February 2

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.

Friday, February 3

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

One Response to Backstage – 1 The Esplanade – Construction Schedule Jan 30 – Feb 3

  1. Pingback: Backstage – 1 The Esplanade – UPDATE for February 1 « L Tower & Backstage Construction Information

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: