8 The Esplanade – Construction Schedule Jan 21 – 28, 2012

This is the current construction schedule for 8 The Esplanade – L Tower for January 21 – 28, 2012

UPDATED January 25, 2012

Saturday, January 21

  • Miscellaneous site work from 9:00 am to 3:00 pm.

Monday, January 23

  • Window delivery at 7:00 am.
  • There will be a 180M concrete pour beginning at 10:00 am which is not expected to extend beyond 7:00 pm.

Tuesday, January 24

  • Window delivery at 7:30 am.
  • There will be a 80M concrete pour beginning at 2:00 pm which is not expected to extend beyond 7:00 pm.

UPDATE: Wednesday, January 25

  • Steel delivery at 7:00 am.
  • There will be a 100M concrete pour beginning at 1:00 pm which may extend beyond 7:00 pm.

UPDATE: Thursday, January 26

  • Steel delivery at 7:00 am.
  • There will be a 90M concrete pour beginning at 1:00 pm which may extend beyond 7:00 pm.

UPDATE: Friday, January 27

  • Steel delivery at 7:00 am.
  • Steel delivery at 10:00 am.

Saturday, January 28

  • At this time – January 25th – no work is scheduled for Saturday.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

One Response to 8 The Esplanade – Construction Schedule Jan 21 – 28, 2012

  1. Pingback: L Tower – Window Deliveries « L Tower & Backstage Construction Information

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: