8 The Esplanade Construction Schedule, Jan 9 – 14
January 8, 2012 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower for January 9 – 14, 2012
Updated January 8, 2012
Monday, January 9
- There will be a Steel Delivery at 9:00 am.
Tuesday, January 10
- There will be a Steel Delivery at 7:00 am.
Wednesday, January 11
- There will be a Steel Delivery at 7:00 am.
- There will be an 180M concrete pour beginning at 10:00 am with the chance of extending beyond 7:00 pm.
Thursday, January 12
- There will be a Steel Delivery at 7:00 am.
- There will be an 90M concrete pour beginning at 2:00 pm with the chance of extending beyond 7:00 pm.
Friday, January 13
- There will be a Steel Delivery at 7:00 am.
- There will be an 80M concrete pour beginning at 2:00 pm with the chance of extending beyond 7:00 pm.
Saturday, January 14
- General work on site from 9:00 am to 4;00 pm, accompanied by 1 paid duty police officer.
* * *
NOTES:
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.