1 The Esplanade – Construction Schedule Jan 9 – 13, 2012
January 6, 2012 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for January 9 – 13, 2012
Posted January 6, 2012
Monday, January 9
- Steel pile delivery at 7:00 am.
- Sub-contractor, Deep Foundation drilling caissons and piles.
- Seven (7) loads of concrete into the site.
- Sub-contractor, GFL delivering an excavator.
Tuesday, January 10
- Sub-contractor, Deep Foundation drilling caissons and piles.
- Seven (7) loads of concrete into the site.
- Sub-contractor, GFL breaking the bridge retaining wall.
Wednesday, January 11
- Sub-contractor, Deep Foundation drilling caissons and piles.
- Seven (7) loads of concrete into the site.
- Sub-contractor, GFL breaking the bridge retaining wall.
Thursday, January 12
- Sub-contractor, Deep Foundation drilling caissons and piles.
- Seven (7) loads of concrete into the site.
- Sub-contractor, GFL breaking the bridge retaining wall.
Friday, January 13
- Sub-contractor, Deep Foundation drilling caissons and piles.
- Seven (7) loads of concrete into the site.
- Sub-contractor, GFL breaking the bridge retaining wall.
* * *
NOTES:
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.