8 The Esplanade – Construction Schedule January 3 – 7, 2012
January 4, 2012 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower for January 3 – 6, 2012
Updated January 4, 2012
Tuesday, January 3
- CANCELLED – There will be a steel Delivery at 7:00 am.
- CANCELLED – There will be an 80M concrete pour beginning at 2:00pm with the chance of extending beyond 7:00 pm.
Wednesday, January 4
- There will be a steel Delivery at 7:00 am.
- CANCELLED – There will be an 80M concrete pour beginning at 2:00 pm with the chance of extending beyond 7:00 pm.
Thursday, January 5
- There will be a steel Delivery at 7:00 am.
- Rescheduled from Wednesday: There will be an 90M concrete pour beginning at 1:00 pm which is not expected to extend beyond 7:00 pm.
Friday, January 6
- There will be a steel Delivery at 7:00 am.
- Rescheduled from Thursday: There will be an 80M concrete pour beginning at 1:00 pm which is not expected to extend beyond 7:00 pm.
Saturday, January 7
- General work on site from 9:00 am to 4;00 pm, accompanied by 1 paid duty police officer.
* * *
* * *
Best wishes for the New Year!
NOTES:
A Paid Duty Police Officer is on-site daily Tuesday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.