Backstage – 1 The Esplanade – UPDATE for February 1

UPDATE January 31, 2012

Wednesday, February 1

  • UPDATE – Sub-contractor GFL Excavating will have three (3) dump trucks removing material from the site at 1 The Esplanade. There will be three (3) truck doing 5 rounds of removal each.
  • For a full listing of construction activity for the week at 1 The Esplanadeplease click here.

L Tower – 8 The Esplanade – Construction Schedule Jan 28 – Feb 4

This is the current construction schedule for 8 The Esplanade – L Tower  for January 30 – February 4, 2012

Posted January 27, 2012

UPDATE: Saturday, January 28

  • 9M concrete pour beginning at 9:00 am.

Monday, January 30

  • Rebar delivery at 7:00 am.
  • Rebar delivery at 10:00 am.

Tuesday, January 31

  • Rebar delivery at 10:00 am.

Wednesday, February 1

  • There will be a 180M concrete pour beginning at 10:00 am, which is NOT expected to extend beyond 7:00 pm.

Thursday, February 2

  • There will be a 90M concrete pour, which is NOT expected to extend beyond 7:00 pm.

Friday, February 3

  • Steel delivery at 7:00 am.
  • Steel delivery at 10:00 am.
  • There will be a 100M concrete pour beginning at 1:00 pm, which may have a slight chance of  extending beyond 7:00 pm.

Saturday, February 4

  • At this time – January 27th – no work is scheduled.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Backstage – 1 The Esplanade – Construction Schedule Jan 30 – Feb 3

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 30 – February 3, 2012

UPDATED January 31, 2012

Monday, January 30

  • Sub-contractor, Deep Foundation will be removing one of the drill rigs from the site, beginning at 7:00 am.
  • At approximately 10:00 am, a semi-trailer with the float for the drill rig will arrive to take it off-site. There will be short-term disruptions to pedestrian and vehicular traffic.
  • The remaining drill rig on site will continue drilling caissons and piles.
  • Five (5) loads of concrete.

Tuesday, January 31

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.

Wednesday, February 1

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.
  • UPDATE – Sub-contractor GFL Excavating will have three (3) dump trucks removing material from the site at 1 The Esplanade. There will be three (3) truck doing 5 rounds of removal each.

Thursday, February 2

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.

Friday, February 3

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

8 The Esplanade – Construction Schedule Jan 21 – 28, 2012

This is the current construction schedule for 8 The Esplanade – L Tower for January 21 – 28, 2012

UPDATED January 25, 2012

Saturday, January 21

  • Miscellaneous site work from 9:00 am to 3:00 pm.

Monday, January 23

  • Window delivery at 7:00 am.
  • There will be a 180M concrete pour beginning at 10:00 am which is not expected to extend beyond 7:00 pm.

Tuesday, January 24

  • Window delivery at 7:30 am.
  • There will be a 80M concrete pour beginning at 2:00 pm which is not expected to extend beyond 7:00 pm.

UPDATE: Wednesday, January 25

  • Steel delivery at 7:00 am.
  • There will be a 100M concrete pour beginning at 1:00 pm which may extend beyond 7:00 pm.

UPDATE: Thursday, January 26

  • Steel delivery at 7:00 am.
  • There will be a 90M concrete pour beginning at 1:00 pm which may extend beyond 7:00 pm.

UPDATE: Friday, January 27

  • Steel delivery at 7:00 am.
  • Steel delivery at 10:00 am.

Saturday, January 28

  • At this time – January 25th – no work is scheduled for Saturday.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

L Tower – Window Deliveries

This coming week – January 23 – 28 – windows will be delivered for the L Tower. There are also currently 3 concrete pours scheduled. Details at: https://ltowerconstructioninfo.com/2012/01/20/8-the-esplanade-construction-schedule-jan-21-28-2012/

For more information on the L Tower:

1 The Esplanade – Construction Schedule Jan 23 – 27, 2012

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 23 – 27, 2012

Posted January 20, 2012

Monday, January 23

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Tuesday, January 24

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Wednesday, January 25

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Thursday, January 26

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Friday, January 27

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

L Tower “Photo of the Day” from Urban Toronto

A nice picture of the L Tower from Front Street is posted on the Urban Toronto website:

Urban Toronto “Photo of the Day” January 20, 2012: http://urbantoronto.ca/news/2012/01/photo-day-l-tower-condos-starts-rise-above-front-street

1 The Esplanade – Construction Schedule Jan 16 – 20, 2012

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 16 – 20, 2012

Posted January 13, 2012

Monday, January 16

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Tuesday, January 17

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Wednesday, January 18

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Thursday, January 19

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Friday, January 20

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

8 The Esplanade – Construction Schedule Jan 16 – 21, 2012

This is the current construction schedule for 8 The Esplanade – L Tower for January 16 – 20, 2012

Posted January 13, 2012

Monday, January 16

  • There will be a 90M concrete pour beginning at 12:00pm with the chance of extending beyond 7:00pm.

Tuesday, January 17

  • There will be a 90M concrete pour beginning at 12:00pm with the chance of extending beyond 7:00pm.

Wednesday, January 18

  • There will be a steel Delivery at 7:00 am.

Thursday, January 19

  • There will be a steel Delivery at 7:00 am.

Friday, January 20

  • There will be a steel Delivery at 7:00 am.
  • There will be a 180M concrete pour beginning at 10:00am which is not expected to extend beyond 7:00 pm.

Saturday, January 21

  • There is no site work scheduled for Saturday

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

L Tower at 23 floors and counting

Photos from January 9, 2012 of the Daniel Libeskind designed L Tower, from Castlepoint, Cityzen and Fernbrook Homes located at 8 The Esplanade – 23 floors and counting:

L Tower looking west from The Esplanade, 1/9/12

 

L Tower at 23 floors, 1/9/12

 

L Tower looking up & NE, 23 stories and rising, 1/9/12

 

L Tower looking east from Platform 1, Union Station Train Shed, 1/9/12