This is the current construction schedule for 8 The Esplanade – L Tower for January 21 – 28, 2012
UPDATED January 25, 2012
Saturday, January 21
- Miscellaneous site work from 9:00 am to 3:00 pm.
Monday, January 23
- Window delivery at 7:00 am.
- There will be a 180M concrete pour beginning at 10:00 am which is not expected to extend beyond 7:00 pm.
Tuesday, January 24
- Window delivery at 7:30 am.
- There will be a 80M concrete pour beginning at 2:00 pm which is not expected to extend beyond 7:00 pm.
UPDATE: Wednesday, January 25
- Steel delivery at 7:00 am.
- There will be a 100M concrete pour beginning at 1:00 pm which may extend beyond 7:00 pm.
UPDATE: Thursday, January 26
- Steel delivery at 7:00 am.
- There will be a 90M concrete pour beginning at 1:00 pm which may extend beyond 7:00 pm.
UPDATE: Friday, January 27
- Steel delivery at 7:00 am.
- Steel delivery at 10:00 am.
Saturday, January 28
- At this time – January 25th – no work is scheduled for Saturday.
* * *
NOTES:
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.