1 The Esplanade – Construction Schedule December 19 – 23

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of December 19 – 23, 2011

Posted December 16, 2011

Monday, December 19

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Tuesday, December 20

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Wednesday, December 21

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Thursday, December 22

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Friday, December 23

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Saturday, December 24

Happy Holidays!

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: