1 The Esplanade – Construction Schedule December 19 – 23
December 16, 2011 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for the week of December 19 – 23, 2011
Posted December 16, 2011
Monday, December 19
- Sub-contractor, Deep Foundation will be installing tie backs.
- Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
- Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.
Tuesday, December 20
- Sub-contractor, Deep Foundation will be installing tie backs.
- Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
- Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.
Wednesday, December 21
- Sub-contractor, Deep Foundation will be installing tie backs.
- Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
- Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.
Thursday, December 22
- Sub-contractor, Deep Foundation will be installing tie backs.
- Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
- Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.
Friday, December 23
- Sub-contractor, Deep Foundation will be installing tie backs.
- Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
- Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.
Saturday, December 24
Happy Holidays!
NOTES:
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.