8 The Esplanade – Construction Schedule December 12 – 17

This is the current construction schedule for 8 The Esplanade – L Tower for the week of December 12 – 17, 2011

Posted December 10, 2011

Monday, December 12

  • There will be a steel Delivery at 7:00am and 90M concrete pour beginning at 2:00pm with the chance of extending beyond 7:00pm

Tuesday, December 13

  • There will be a steel delivery at 7:00 am.

Wednesday, December 14

  • There will be a steel delivery at 7:00 am.

Thursday, December 15

  • There will be an 180M concrete pour beginning at 10:00am not expected to go beyond 7:00pm

Friday, December 16

  • There will be a steel delivery at 7:00am and 80M concrete pour beginning at 2:00pm with the chance of extending beyond 7:00pm

Saturday, December 17

  • Premform Working on Site from 9:00-2:00pm
  • 1 Paid Duty Officer is scheduled to be on-site.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: