1 The Esplanade – Construction Schedule December 12 – 16
December 9, 2011 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for the week of December 12 – 16, 2011
Posted December 9, 2011
Monday, December 12
- Sub-contractor Deep Foundation will be installing tie backs.
- Sub-contractor GFL Excavating removing bulk. 5 dump trucks 5 rounds each.
Tuesday, December 13
- Sub-contractor Deep Foundation will be installing tie backs.
- Sub-contractor GFL Excavating removing bulk. 5 dump trucks 5 rounds each.
Wednesday, December 14
- Sub-contractor Deep Foundation will be installing tie backs.
- Sub-contractor GFL Excavating removing bulk. 5 dump trucks 5 rounds each.
Thursday, December 15
- Sub-contractor Deep Foundation will be installing tie backs.
- Deep Foundation delivering drill rig with police escort.
- Sub-contractor GFL Excavating removing bulk. 5 dump trucks 5 rounds each.
Friday, December 16
- Sub-contractor Deep Foundation will be installing tie backs.
- Deep Foundations drilling piles and caissons. 5 concrete truckloads.
- Sub-contractor GFL Excavating removing bulk. 5 dump trucks 5 rounds each.
NOTES:
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.