1 The Esplanade – Construction Schedule December 12 – 16

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of December 12 – 16, 2011

Posted December 9, 2011

Monday, December 12

  • Sub-contractor Deep Foundation will be installing tie backs.
  • Sub-contractor GFL Excavating removing bulk. 5 dump trucks 5 rounds each.

Tuesday, December 13

  • Sub-contractor Deep Foundation will be installing tie backs.
  • Sub-contractor GFL Excavating removing bulk. 5 dump trucks 5 rounds each.

Wednesday, December 14

  • Sub-contractor Deep Foundation will be installing tie backs.
  • Sub-contractor GFL Excavating removing bulk. 5 dump trucks 5 rounds each.

Thursday, December 15

  • Sub-contractor Deep Foundation will be installing tie backs.
  • Deep Foundation delivering drill rig with police escort.
  • Sub-contractor GFL Excavating removing bulk. 5 dump trucks 5 rounds each.

Friday, December 16

  • Sub-contractor Deep Foundation will be installing tie backs.
  • Deep Foundations drilling piles and caissons. 5 concrete truckloads.
  • Sub-contractor GFL Excavating removing bulk. 5 dump trucks 5 rounds each.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: