8 The Esplanade – Construction Schedule November 21 – 26

This is the current construction schedule for 8 The Esplanade – L Tower for the week of November 21 – 26, 2011

Posted November 21, 2011

Monday, November 21

  • A steel delivery was scheduled to occur at 7:00 am.

Tuesday, November 22

  • There will be an 180M Concrete Pour beginning at 10 am, which is not expected to go past 7:00 pm.

Wednesday, November 23

  • There will be a steel delivery at 7:00 am.
  • There will be an 80M Concrete Pour beginning at 2:00 pm, which may go past 7:00 pm.

Thursday, November 24

  • There will be a steel delivery at 7:00 am.
  • There will be an 80M Concrete Pour beginning at 1:00 pm, which may go past 7:00 pm.

Friday, November 25

  • There will be a steel delivery at 7:00 am.

Saturday, November 26

  • Sub-contractor, Premform, will be working on-site from 9:00 am – 2:00 pm.
  • 1 Paid Duty Officer is scheduled to be on-site.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: