1 The Esplanade November 21 – 25
November 21, 2011 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of November 21 – 25, 2011
Posted November 21, 2011
No significant construction activity will occur on the site Monday through Wednesday as the first stage of bulk excavation is complete.
Tie back installation will start on Thursday or Friday of this week. An update will be posted as information becomes available.
ALSO:
For another look at recent images of the construction site from Urban Toronto: please click here.