1 The Esplanade Construction Schedule November 7 – 9

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of November 7 – 9, 2011

Posted November 5, 2011

For example images of this work please click here.

Monday, November 7

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.

    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse  into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.

Tuesday, November 8

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse  into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.

Wednesday, November 9

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.
NOTES:
  • Bulk excavating should be complete at 1 The Esplanade on Wednesday, November 9.  
  • Following the excavation work, sub-contractor, Deep Foundation, will start the first row tie back installation. An update on will be provided once information is available.
  • Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm daily to assist with traffic control.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: