Schedule for 8 The Esplanade October 31 – November 5

This is the current construction schedule for 8 The Esplanade – L Tower for the week of October 31 through November 4, 2011

Posted November 3, 2011

Monday, October 31

  • There will be a 70M Concrete Pour starting at 1:00 pm, which is not expected to go beyond 7:00 pm.

Tuesday, November 1

  • There will be a steel delivery at 7:00 am.
  • There will be a 10M Concrete Pour starting at 11:00 am, which is not expected to go beyond 7:00 pm.

Wednesday, November 2

  • There will be a steel delivery at 7:00 am.

Thursday, November 3

  • There will be a steel delivery at 7:00 am.
  • UPDATED: There will be an 180M Concrete Pour starting at approximately 10:00 am,  with the possibility of extending beyond 7:00pm

Friday, November 4

  • There will be a steel delivery at 7:00 am.
  • UPDATED: There will be an 80M Concrete Pour starting at 1:00 pm,  with the possibility of extending beyond 7:00pm

Saturday, November 5

  • UPDATED: Sub-contractor, Premform, will be working on-site from 9:00 am – 2:00 pm.
NOTES:
  • A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm daily to assist with traffic control.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: