Schedule for 8 The Esplanade October 31 – November 5
November 3, 2011 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – for the week of October 31 through November 4, 2011
Posted November 3, 2011
Monday, October 31
- There will be a 70M Concrete Pour starting at 1:00 pm, which is not expected to go beyond 7:00 pm.
Tuesday, November 1
- There will be a steel delivery at 7:00 am.
- There will be a 10M Concrete Pour starting at 11:00 am, which is not expected to go beyond 7:00 pm.
Wednesday, November 2
- There will be a steel delivery at 7:00 am.
Thursday, November 3
- There will be a steel delivery at 7:00 am.
- UPDATED: There will be an 180M Concrete Pour starting at approximately 10:00 am, with the possibility of extending beyond 7:00pm
Friday, November 4
- There will be a steel delivery at 7:00 am.
- UPDATED: There will be an 80M Concrete Pour starting at 1:00 pm, with the possibility of extending beyond 7:00pm
Saturday, November 5
- UPDATED: Sub-contractor, Premform, will be working on-site from 9:00 am – 2:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm daily to assist with traffic control.