8 The Esplanade – Construction Schedule November 28 – December 3

This is the current construction schedule for 8 The Esplanade – L Tower for the week of November 28 – December 3, 2011

Posted November 30, 2011

Monday, November 28

  • There will be a steel delivery at 7:00 am.

Tuesday, November 29

  • The 180M Concrete Pour was cancelled due to inclement weather. 

Wednesday, November 30

  • Rescheduled from Tuesday: There will be an 180M Concrete Pour beginning at 10:00 am, which is not expected to go past 7:00 pm.

Thursday, December 1

  • There will be a steel delivery at 7:00 am.
  • There will be an 80M Concrete Pour beginning at 2:00 pm, which may go past 7:00 pm.

Friday, December 2

  • There will be a steel delivery at 7:00 am.
  • There will be an 80M Concrete Pour beginning at 2:00 pm, which may go past 7:00 pm.

Saturday, December 3

  • Sub-contractor, Premform, will be working on-site from 9:00 am – 2:00 pm.
  • 1 Paid Duty Officer is scheduled to be on-site.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade – Construction Schedule November 28 – December 2

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of November 28 – December 2, 2011

Posted November 25, 2011

Monday, November 28

  • Sub-contractor Deep Foundation will be installing tie backs.

Tuesday, November 29

  • Sub-contractor Deep Foundation will be installing tie backs.

Wedensday, November 30

  • Sub-contractor Deep Foundation will be installing tie backs.

Thursday, December 1

  • Sub-contractor Deep Foundation will be installing tie backs.

Friday, December 2

  • Sub-contractor Deep Foundation will be installing tie backs.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

8 The Esplanade – Construction Schedule November 21 – 26

This is the current construction schedule for 8 The Esplanade – L Tower for the week of November 21 – 26, 2011

Posted November 21, 2011

Monday, November 21

  • A steel delivery was scheduled to occur at 7:00 am.

Tuesday, November 22

  • There will be an 180M Concrete Pour beginning at 10 am, which is not expected to go past 7:00 pm.

Wednesday, November 23

  • There will be a steel delivery at 7:00 am.
  • There will be an 80M Concrete Pour beginning at 2:00 pm, which may go past 7:00 pm.

Thursday, November 24

  • There will be a steel delivery at 7:00 am.
  • There will be an 80M Concrete Pour beginning at 1:00 pm, which may go past 7:00 pm.

Friday, November 25

  • There will be a steel delivery at 7:00 am.

Saturday, November 26

  • Sub-contractor, Premform, will be working on-site from 9:00 am – 2:00 pm.
  • 1 Paid Duty Officer is scheduled to be on-site.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade November 21 – 25

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of November 21 – 25, 2011

Posted November 21, 2011

No significant construction activity will occur on the site Monday through Wednesday as the first stage of bulk excavation is complete.

Tie back installation will start on Thursday or Friday of this week. An update will be posted as information becomes available.

ALSO:

For another look at recent images of the construction site from Urban Toronto: please click here.

8 The Esplanade Construction Schedule November 14 – 19

This is the current construction schedule for 8 The Esplanade – L Tower for the week of November 14 – 19, 2011

Posted November 15, 2011

Monday, November 14

  • There will be a steel delivery at 7:00 am.
  • There will be an 80M Concrete Pour beginning at 1 pm with possibility that it may extend beyond 7:00 pm.

Tuesday, November 15

  • There will be a steel delivery at 7:00 am.
  • There will be an 80M Concrete Pour beginning at 1 pm with possibility that it may extend beyond 7:00. pm

Wednesday, November 16

  • There will be a steel delivery at 7:00 am.
  • There will be an 80M Concrete Pour beginning at 2:00 pm, which may go past 7:00 pm.

Thursday, November 17

  • There will be an 110M Concrete Pour beginning at 2:00 pm, which may go past 7:00 pm.

Friday, November 18

  • There will be a steel delivery at 7:00 am.
  • There will be an 30M Concrete Pour beginning at 1:00 pm, which is not expected to go past 7:00.

Saturday, November 19

  • Sub-contractor, Premform, will be working on-site from 9:00 am – 2:00 pm.
  • 1 Paid Duty Officer is scheduled to be on-site.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade Construction Schedule November 14 – 18

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of November 14 – 18, 2011

Posted November 14, 2011

For example images of this work please click here.

Monday, November 14

  • Sub-contractor GFL will be doing bulk excavating. There will be 4 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse  into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site

 

Tuesday, November 15

  • Sub-contractor GFL will be doing bulk excavating. There will be 4 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse  into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.
  • Sub-contractor Deep Foundation will be delivering the tie back drill.

 

Wednesday, November 16

  • Sub-contractor GFL will be doing bulk excavating. There will be 4 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.
  • Sub-contractor Deep Foundation will installing the test tie back.

 

Thursday, November 17

  • Sub-contractor GFL will be doing bulk excavating. There will be 4 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.

 

Friday, November 18

  • Sub-contractor GFL will be doing bulk excavating. There will be 4 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.

 

NOTES:

  • Bulk excavating is still underway this week. 
  • Paid Duty Police Officer is on-site daily Monday to Friday from 7:00 am to 4:00 pm daily to assist with traffic control.

Urban Toronto feature on the L Tower

L Tower: The Countdown Begins: http://urbantoronto.ca/news/2011/11/l-tower-countdown-begins

1 The Esplanade Construction Schedule November 7 – 9

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of November 7 – 9, 2011

Posted November 5, 2011

For example images of this work please click here.

Monday, November 7

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.

    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse  into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.

Tuesday, November 8

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse  into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.

Wednesday, November 9

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.
NOTES:
  • Bulk excavating should be complete at 1 The Esplanade on Wednesday, November 9.  
  • Following the excavation work, sub-contractor, Deep Foundation, will start the first row tie back installation. An update on will be provided once information is available.
  • Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm daily to assist with traffic control.

8 The Esplanade Construction Schedule November 7 – 12

This is the current construction schedule for 8 The Esplanade – L Tower for the week of November 7 – 12 2011

Posted November 5, 2011

Monday, November7

  • There will be a steel delivery at 7:00 am.
  • There will be a Concrete Pour starting at 2:00 pm, with the possibility ofextending beyond 7:00pm.

Tuesday, November 8

  • There will be a steel delivery at 7:00 am.

Wednesday, November 9

  • There will be a steel delivery at 7:00 am.

Thursday, November 10

  • There will be a steel delivery at 7:00 am.
  •  There will be an 180M Concrete Pour starting at 12:00 pm (noon),  with the possibility of extending beyond 7:00pm

Friday, November 11

  • There will be a steel delivery at 7:00 am.

Saturday, November 12

  •  Sub-contractor, Premform, will be working on-site from 9:00 am – 2:00 pm.
  • 1 Paid Duty Police Office on-site.
NOTES:
  • A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm daily to assist with traffic control.

Schedule for 8 The Esplanade October 31 – November 5

This is the current construction schedule for 8 The Esplanade – L Tower for the week of October 31 through November 4, 2011

Posted November 3, 2011

Monday, October 31

  • There will be a 70M Concrete Pour starting at 1:00 pm, which is not expected to go beyond 7:00 pm.

Tuesday, November 1

  • There will be a steel delivery at 7:00 am.
  • There will be a 10M Concrete Pour starting at 11:00 am, which is not expected to go beyond 7:00 pm.

Wednesday, November 2

  • There will be a steel delivery at 7:00 am.

Thursday, November 3

  • There will be a steel delivery at 7:00 am.
  • UPDATED: There will be an 180M Concrete Pour starting at approximately 10:00 am,  with the possibility of extending beyond 7:00pm

Friday, November 4

  • There will be a steel delivery at 7:00 am.
  • UPDATED: There will be an 80M Concrete Pour starting at 1:00 pm,  with the possibility of extending beyond 7:00pm

Saturday, November 5

  • UPDATED: Sub-contractor, Premform, will be working on-site from 9:00 am – 2:00 pm.
NOTES:
  • A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm daily to assist with traffic control.