8 The Esplanade Construction Schedule October 22 – 28

This is the current construction schedule for 8 The Esplanade – L Tower for the week of October 22 – 28, 2011

Posted October 28, 2011

Saturday, October 22
  • Sub-contractor, Premform, will be working on-site from 9:00 am – 2:00 pm.
  • 1 Paid Duty Officer is scheduled to be on-site.

Monday, October 24

  • There will be a steel delivery at 7:00 am.

Tuesday, October 25

  • There will be a steel delivery at 7:00 am.

Wednesday, October 26

  • There will not be a steel delivery at 7:00 am.
  • There will be an 180M Concrete Pour now scheduled to start at 8:00 am, with the continued, though slight, possibility of the pour extending beyond 7:00pm

Thursday, October 27

  • There will be a steel delivery at 7:00 am.
  • There will be a 72M Concrete Pour starting at 1:00pm, which is not expected to go beyond 7:00 pm.
Friday, October 28
  • There will be a steel delivery at 7:00 am.
  • A late delivery of concrete will mean that the  72M Concrete Pour will likely extend beyond 7:00pm
NOTES:
  • A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm daily to assist with traffic control.
  • A security guard on-site from 4:00 pm – 6:00 am daily.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: