Schedule for 1 The Esplanade October 31 – November 4

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of October 31 – November 4, 2011

Posted October 29, 2011

For example images of this work please click here.

 

Monday, October 31

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.

    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse  into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.

Tuesday, November 1

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse  into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.

Wednesday, November 2

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.

Thursday, November 3

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.

Friday, November 4

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.
NOTES:
  • A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm daily to assist with traffic control.

Bulk Excavation and Removal at 1 The Esplanade

GFL Truck entering The Esplanade from Yonge Street

Paid-Duty Officer halting traffic after GFL Truck enters The Esplanade from Yonge Street

GFL Truck reversing into the site at 1 The Esplanade

Loading the truck with excavated soil from 1 The Esplanade

Loading a GFL truck with excavated soil at 1 The Esplanade

Fully loaded GFL Truck departing eastbound from 1 The Esplanade

8 The Esplanade Construction Schedule October 22 – 28

This is the current construction schedule for 8 The Esplanade – L Tower for the week of October 22 – 28, 2011

Posted October 28, 2011

Saturday, October 22
  • Sub-contractor, Premform, will be working on-site from 9:00 am – 2:00 pm.
  • 1 Paid Duty Officer is scheduled to be on-site.

Monday, October 24

  • There will be a steel delivery at 7:00 am.

Tuesday, October 25

  • There will be a steel delivery at 7:00 am.

Wednesday, October 26

  • There will not be a steel delivery at 7:00 am.
  • There will be an 180M Concrete Pour now scheduled to start at 8:00 am, with the continued, though slight, possibility of the pour extending beyond 7:00pm

Thursday, October 27

  • There will be a steel delivery at 7:00 am.
  • There will be a 72M Concrete Pour starting at 1:00pm, which is not expected to go beyond 7:00 pm.
Friday, October 28
  • There will be a steel delivery at 7:00 am.
  • A late delivery of concrete will mean that the  72M Concrete Pour will likely extend beyond 7:00pm
NOTES:
  • A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm daily to assist with traffic control.
  • A security guard on-site from 4:00 pm – 6:00 am daily.

L Tower rising to 14 floors

image

The construction team is now working on the 14th floor of the L Tower; seen here looking up from The Esplanade, October 25, 2011.

Construction Schedule for 1 The Esplanade October 24 – 28

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of October 24 – 28, 2011

Posted October 24, 2011

Monday, October 24

  • No activity is scheduled for Monday at 1 The Esplanade.

Tuesday, October 25

  • Sub-contractor GFL will be removing bulk from the site. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street. 

Wednesday, October 26

  • Sub-contractor GFL will be removing bulk from the site. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.

Thursday, October 27

  • Sub-contractor GFL will be removing bulk from the site. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
Friday, October 28
  • Sub-contractor GFL will be removing bulk from the site. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
NOTES:
  • A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm daily to assist with traffic control.

8 The Esplanade Construction Schedule – October 17 – 21

This is the current construction schedule for 8 The Esplanade – L Tower for the week of October 17 – 22, 2011

Posted October 20, 2011

Monday, October 17

There will be a 90M concrete pour, which may go beyond 7:00 pm.

Tuesday, October 18

There will be a 90M concrete pour, which may go beyond 7:00 pm.

Wednesday, October 19

No concrete is scheduled for today.

Thursday, October 20

No concrete is scheduled for today.

Friday, October 21

No concrete is scheduled for today.

NOTE 1: Several daily deliveries throughout the week with little or no impact on traffic.
NOTE 2. A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday. A security guard on site from 4:00 pm – 6:00 am daily.

L Tower rising – October 18/11

image

The L Tower condominium can be seen in this photograph by EN Consulting Associate, Chris Drew, as it continues to rise floor by floor. The view is looking east from the Metrolinx – GO Bus terminal – October 18/11.

Update for 1 The Esplanade – October 18 – 22

As of Tuesday, October 18, GFL Excavating will start bulk excavating at 1 The Esplanade.

This work is required to create the space for the foundation for the Backstage condominium and the underground parking for the L Tower.

There will be seven dump trucks each doing five loads during day. This work will have short-term but significant impacts on pedestrian and vehicular traffic in the area of Scott and The Esplanade during the work day. The construction management team apologizes in advance for any inconvenience this may cause.

Please check back through the week for updates.

1 The Esplanade Construction Schedule for October 17- 22

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condo for the week of October 17 – 22, 2011

Posted October 16, 2011

Please Note: The bulk excavating is schedule to get underway this week. Once it is in full operation, there will be high impact on traffic at Scott Street and The Esplanade due to a large number of dump trucks coming to and leaving the site. At this time there remains no firm schedule. This site will be updated as soon as this information becomes available.

8 The Esplanade Construction Schedule – October 10 – 15

This is the current construction schedule for 8 The Esplanade – L Tower for the week of October 10 – 14, 2011

Posted October 15, 2011

Monday, October 10

Happy Thanksgiving!

Tuesday, October 11
No concrete is scheduled for today.

Wednesday, October 12

No concrete is scheduled for today.

Thursday, October 13

No concrete scheduled for today.

Friday, October 14

There will be a 180M concrete pour, which may go beyond 7:00 pm.

Saturday, October 15

Dominus and premform will work on the site from 9:00 am to 2:00 pm.

NOTE 1: Several daily deliveries throughout the week with little or no impact on traffic.
NOTE 2. A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday. A security guard on site from 4:00 pm – 6:00 am daily.