Construction Schedule September 10 – September 16

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 29 through September 2, 2011.

Posted: 9 September 2011

Saturday, September 10

8 The Esplanade – L Tower 

  • Premform and Dominus will work from 9:00 am – 4:00 pm.

1 The Esplanade – L Tower Parking + Backstage 

  • No construction activity is scheduled.

Monday, September 12

8 The Esplanade – L Tower 

  • There will be a 45M concrete pour which is not expected to go beyond 7:00pm.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete accessing The Esplanade.

Tuesday, September 13

8 The Esplanade – L Tower

  • No concrete scheduled.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete accessing The Esplanade.

Wednesday, September 14

8 The Esplanade – L Tower 

  • No concrete scheduled.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Thursday, September 15

8 The Esplanade – L Tower 

  • There is a 90M concrete pour that may go past 7:00 pm.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
Friday, September 16
8 The Esplanade – L Tower 
  • If Thursday’s concrete pour is not ready, there will be a 90M pour which may go past 7:00 pm.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
NOTE 1:  Several daily deliveries throughout the week with little or no impact on traffic. 
NOTE 2. A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday. A  security guard on site from 4:00 pm – 6:00 am daily.

Apology for early morning Labour Day Weekend work

A new contractor who is not familiar with the rules on working hours worked this past Sunday,  September 4, on their own without Dominus’ knowledge. This contractor has now been informed  regarding the proper working hours, and has assured construction manager Dominus that this will not happen again.

Dominus is committed to observing all City by-laws and regulations regarding construction working hours and will be even more diligent in future to ensure that all our contractors are properly informed and comply.

Dominus and the construction management team apologize for any convenience caused.

 

UrbanToronto Covers the Progress at Backstage

The UrbanToronto forum website had an article today regarding the progress of the Backstage condominium.

 

Shoring Underway at Cityzen, Fernbrook, and Castlepoint’s Backstage Condos

September 6, 2011 12:00 pm | by Craig White

Ground was broken several months ago now at the construction site for Backstage on the Esplanade, the 36-storey condominium tower by Cityzen, Fernbrook Homes, and Castelpoint Realty Partners. The Page + Steele Archtiects-designed tower will rise on a tight site, hemmed in by Yonge Street, The Esplanade, Union Station’s rail tracks, and 25 The Esplanade, while still preserving views of 25 The Esplanade’s famous bullnose.

The full article is here.

Updated: Construction Schedule September 5 – September 9

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of September 5 through September 9, 2011.

Updated: 6 September 2011

Monday, September 5

8 The Esplanade – L Tower

  • No concrete is scheduled as of September 2.

1 The Esplanade – L Tower Parking + Backstage 

  • No work scheduled.

 Tuesday, September 6

8 The Esplanade – L Tower 

  • There will be a Steel Delivery at 7:00am.

1 The Esplanade – L Tower Parking + Backstage (Updated)

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.  There will be 10 loads of concrete accessing the site from The Esplanade.
  • GFL Excavating will be removing 16 loads of dirt.

Wednesday, September 7

8 The Esplanade – L Tower

  • There will be a 45M concrete pour starting at 1:00pm and it is not expected to go beyond 7:00pm.

1 The Esplanade – L Tower Parking + Backstage  (Updated)

  • There will be a steel pile delivery by a regular semi-tractor trailer.
  • Sub-contractor, Deep Foundation will be drilling caissons and piles.  There will be 10 loads of concrete accessing the site from The Esplanade.

Thursday, September 8

8 The Esplanade – L Tower 

  • There will be a steel delivery at 7:00am and 27M concrete pour starting at 1:00pm that is not expected to go beyond 7:00pm

1 The Esplanade – L Tower Parking + Backstage (Updated)

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.  There will be 10 loads of concrete accessing the site from The Esplanade.

Friday, September 9

8 The Esplanade – L Tower 

  • There will be a steel Delivery at 7:00am and 144M Concrete Pour starting at 11:00 that is not expected to go beyond 7:00pm.

1 The Esplanade – L Tower Parking + Backstage (Updated)

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.  There will be 10 loads of concrete accessing the site from The Esplanade.
NOTE 1:  Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday.