Construction Schedule October 3 – 7

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of October 3 – 7, 2011

 

Posted: September 30, 2011

 

Monday, October 3

 

8 The Esplanade – L Tower

  • There will be a 180M concrete pour, which may go beyond 7:00 pm.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Tuesday, October 4

 

8 The Esplanade – L Tower

  • There will be a 90M concrete pour, which may go beyond 7:00 pm.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Wednesday, October 5

 

8 The Esplanade – L Tower

  • There will be a 90M concrete pour, which may go beyond 7:00 pm.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Thursday, October 6

 

8 The Esplanade – L Tower

  • There will be a 72M concrete pour, which may go beyond 7:00 pm.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be dismantling the drill rig on site.

Friday, October 7

 

8 The Esplanade – L Tower
  • No concrete scheduled.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be dismantling the crane on site.
NOTE 1: Several daily deliveries throughout the week with little or no impact on traffic.
NOTE 2. A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday. A security guard on site from 4:00 pm – 6:00 am daily.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: