Construction Schedule October 3 – 7
September 30, 2011 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of October 3 – 7, 2011
Posted: September 30, 2011
Monday, October 3
8 The Esplanade – L Tower
- There will be a 180M concrete pour, which may go beyond 7:00 pm.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.
Tuesday, October 4
8 The Esplanade – L Tower
- There will be a 90M concrete pour, which may go beyond 7:00 pm.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.
Wednesday, October 5
8 The Esplanade – L Tower
- There will be a 90M concrete pour, which may go beyond 7:00 pm.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.
Thursday, October 6
8 The Esplanade – L Tower
- There will be a 72M concrete pour, which may go beyond 7:00 pm.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be dismantling the drill rig on site.
Friday, October 7
- No concrete scheduled.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be dismantling the crane on site.