Construction Schedule September 26 – October 1, 2011
September 30, 2011 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of September 26 – October 1, 2011
Posted: September 30, 2011
Monday, September 26
8 The Esplanade – L Tower
- There will be a 72M concrete pour, which may go beyond 7:00 pm.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete accessing The Esplanade.
Tuesday, September 27
8 The Esplanade – L Tower
- There will be a 100M concrete pour, which may go beyond 7:00 pm.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete accessing The Esplanade.
Wednesday, September 28
8 The Esplanade – L Tower
- There will be a 72M concrete pour, which may go beyond 7:00 pm.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.
Thursday, September 29
8 The Esplanade – L Tower
- No concrete scheduled.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.
- No concrete scheduled.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.
- Sub-Contractor Deep Foundation has scheduled an 85-foot steel pile delivery at Noon.
Saturday, October 1
8 The Esplanade – L Tower
- Dominus site labour in 9:00 am – 1:00 pm to perform housekeeping duties.
- Sub-contractor, Premform will work from on the site from 9:00 am – 4:00 pm.
1 The Esplanade – L Tower Parking + Backstage
- No construction activity is scheduled.