Construction Schedule September 26 – October 1, 2011

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of September 26 – October 1, 2011

Posted: September 30, 2011

Monday, September 26

8 The Esplanade – L Tower

  • There will be a 72M concrete pour, which may go beyond 7:00 pm.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete accessing The Esplanade.

Tuesday, September 27

8 The Esplanade – L Tower

  • There will be a 100M concrete pour, which may go beyond 7:00 pm.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete accessing The Esplanade.

Wednesday, September 28

8 The Esplanade – L Tower

  • There will be a 72M concrete pour, which may go beyond 7:00 pm.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Thursday, September 29

8 The Esplanade – L Tower

  • No concrete scheduled.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
Friday, September 30
8 The Esplanade – L Tower
  • No concrete scheduled.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
  • Sub-Contractor Deep Foundation has scheduled an 85-foot steel pile delivery at Noon. 

Saturday, October 1

8 The Esplanade – L Tower

  • Dominus site labour in 9:00 am – 1:00 pm to perform housekeeping duties.
  • Sub-contractor, Premform will work from on the site from 9:00 am – 4:00 pm.

1 The Esplanade – L Tower Parking + Backstage

  • No construction activity is scheduled.
NOTE 1: Several daily deliveries throughout the week with little or no impact on traffic.
NOTE 2. A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday. A security guard on site from 4:00 pm – 6:00 am daily.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: