Construction Schedule – September 19 – 23, 2011
September 18, 2011 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of September 19 – 23, 2011.
Posting Date: September 18, 2011
Monday, September 19
8 The Esplanade – L Tower
- There will be a 72M concrete pour which is not expected to go past 7:00 pm
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete accessing The Esplanade.
- Deep Foundation has schedule an 85 foot steel pile delivery for the afternoon at approximately 2:00 pm.
- There will be some temporary impact on vehicular and pedestrian traffic in the area of Scott Street and The Esplanade.
Tuesday, September 20
8 The Esplanade – L Tower
- There will be a 45M concrete pour which is not expected to go past 7:00 pm
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete accessing The Esplanade.
Wednesday, September 21
8 The Esplanade – L Tower
- No concrete pour is scheduled as of posting date – September 18, 2011.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.
- GFL Excavating will be removing spoils from the site: 4 trucks taking 16 loads.
Thursday, September 22
8 The Esplanade – L Tower
- No concrete pour is scheduled as of posting date – September 18, 2011.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.
- GFL Excavating will be removing spoils from the site: 4 trucks taking 16 loads.
Friday, September 23
8 The Esplanade – L Tower
- No concrete pour is scheduled as of posting date – September 18, 2011.
1 The Esplanade – L Tower Parking + Backstage
- Sub-contractor, Deep Foundation will be drilling caissons and piles.
- There will be 10 loads of concrete delivered throughout the day.
NOTE 1: Several daily deliveries throughout the week with little or no impact on traffic.
NOTE 2. A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday. A security guard on site from 4:00 pm – 6:00 am daily.