Construction Schedule – September 19 – 23, 2011

 

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of September 19 – 23, 2011.

Posting Date: September 18, 2011

Monday, September 19

8 The Esplanade – L Tower

  • There will be a 72M concrete pour which is not expected to go past 7:00 pm

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete accessing The Esplanade.
  • Deep Foundation has schedule an 85 foot steel pile delivery for the afternoon at approximately  2:00 pm.
    • There will be some temporary impact on vehicular and pedestrian traffic in the area of Scott Street and The Esplanade.

Tuesday, September 20

8 The Esplanade – L Tower

  • There will be a 45M concrete pour which is not expected to go past 7:00 pm

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete accessing The Esplanade.

Wednesday, September 21

8 The Esplanade – L Tower

  • No concrete pour is scheduled as of posting date – September 18, 2011.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
  • GFL Excavating will be removing spoils from the site: 4 trucks taking 16 loads.

Thursday, September 22

8 The Esplanade – L Tower

  • No concrete pour is scheduled as of posting date – September 18, 2011.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
  • GFL Excavating will be removing spoils from the site: 4 trucks taking 16 loads.

Friday, September 23

8 The Esplanade – L Tower

  • No concrete pour is scheduled as of posting date – September 18, 2011.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

NOTE 1: Several daily deliveries throughout the week with little or no impact on traffic.
NOTE 2. A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday. A security guard on site from 4:00 pm – 6:00 am daily.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: