Construction Schedule September 10 – September 16

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 29 through September 2, 2011.

Posted: 9 September 2011

Saturday, September 10

8 The Esplanade – L Tower 

  • Premform and Dominus will work from 9:00 am – 4:00 pm.

1 The Esplanade – L Tower Parking + Backstage 

  • No construction activity is scheduled.

Monday, September 12

8 The Esplanade – L Tower 

  • There will be a 45M concrete pour which is not expected to go beyond 7:00pm.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete accessing The Esplanade.

Tuesday, September 13

8 The Esplanade – L Tower

  • No concrete scheduled.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete accessing The Esplanade.

Wednesday, September 14

8 The Esplanade – L Tower 

  • No concrete scheduled.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Thursday, September 15

8 The Esplanade – L Tower 

  • There is a 90M concrete pour that may go past 7:00 pm.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
Friday, September 16
8 The Esplanade – L Tower 
  • If Thursday’s concrete pour is not ready, there will be a 90M pour which may go past 7:00 pm.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
NOTE 1:  Several daily deliveries throughout the week with little or no impact on traffic. 
NOTE 2. A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday. A  security guard on site from 4:00 pm – 6:00 am daily.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: