Updated: Construction Schedule September 5 – September 9

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of September 5 through September 9, 2011.

Updated: 6 September 2011

Monday, September 5

8 The Esplanade – L Tower

  • No concrete is scheduled as of September 2.

1 The Esplanade – L Tower Parking + Backstage 

  • No work scheduled.

 Tuesday, September 6

8 The Esplanade – L Tower 

  • There will be a Steel Delivery at 7:00am.

1 The Esplanade – L Tower Parking + Backstage (Updated)

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.  There will be 10 loads of concrete accessing the site from The Esplanade.
  • GFL Excavating will be removing 16 loads of dirt.

Wednesday, September 7

8 The Esplanade – L Tower

  • There will be a 45M concrete pour starting at 1:00pm and it is not expected to go beyond 7:00pm.

1 The Esplanade – L Tower Parking + Backstage  (Updated)

  • There will be a steel pile delivery by a regular semi-tractor trailer.
  • Sub-contractor, Deep Foundation will be drilling caissons and piles.  There will be 10 loads of concrete accessing the site from The Esplanade.

Thursday, September 8

8 The Esplanade – L Tower 

  • There will be a steel delivery at 7:00am and 27M concrete pour starting at 1:00pm that is not expected to go beyond 7:00pm

1 The Esplanade – L Tower Parking + Backstage (Updated)

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.  There will be 10 loads of concrete accessing the site from The Esplanade.

Friday, September 9

8 The Esplanade – L Tower 

  • There will be a steel Delivery at 7:00am and 144M Concrete Pour starting at 11:00 that is not expected to go beyond 7:00pm.

1 The Esplanade – L Tower Parking + Backstage (Updated)

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.  There will be 10 loads of concrete accessing the site from The Esplanade.
NOTE 1:  Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: